Well No. 23

Yrybucua Central Church

 Technical Details

 

Sponsor:    Dalton First United Methodist Church, Dalton, Georgia

Drilling date: Oct 31-Nov 14, 2007

Location:   Latitude -   S24° 28.787’       Longitude - W 056° 05.195' 

Elevation:     183 meters above mean sea level

Total cost:    $1,715

Drill depth:  47.1 meters

Soil types encountered:    clayey sand and sandstone

Static groundwater level: 10.2 meters below top of casing

Dynamic groundwater level:  N/A - hand pump

Installed well depth:  46.1 meters

Length of screened section:  18 meters

Length of gravel packed section:   27 meters

Length and type of sealed section:  1 meter of bentonite pellets

Pump description:    Hand pump

Depth to base of pump:   36 meters

Flow rate:    N/A - hand pump

 