Well No. 11
Primera Linea Methodist Church
Technical Details
Sponsor: Firebaugh/Mendota United Methodist Church - Firebaugh, California
Drilling date: October 15-21, 2004
Location: Latitude - S 24° 27.144' Longitude - W 56° 03.944'
Elevation: 243 meters above sea level
Total cost: $3,021
Drill depth: 83.6 meters (275 ft.)
Soil types encountered: sand, soft to stiff clays, thin layers of iron precipitate, soft sandstone at depth
Static groundwater level: 49.8 meters
Dynamic groundwater level: 54 meters
Installed well depth: 81.6 meters
Length of screened section: 18 meters
Length of gravel packed section: approximately 20 meters
Length and type of sealed section: Approx. 1 meter of bentonite pellets
Pump description: 1.0 hp mono-phase electric submersible
Depth to base of pump: 76 meters
Flow rate: 2,300 liters/hour
Water analysis results: Not yet tested
|