Well No. 11

Primera Linea Methodist Church

 Technical Details

 

Sponsor:    Firebaugh/Mendota United Methodist Church - Firebaugh, California

Drilling date: October 15-21, 2004

Location:   Latitude -  S 24° 27.144'     Longitude - W 56° 03.944'

Elevation:     243 meters above sea level

Total cost:    $3,021

Drill depth:    83.6 meters (275 ft.)

Soil types encountered:   sand, soft to stiff clays, thin layers of iron precipitate, soft sandstone at depth

Static groundwater level:     49.8  meters

Dynamic groundwater level:      54 meters

Installed well depth:  81.6 meters

Length of screened section:   18 meters

Length of gravel packed section:  approximately 20  meters

Length and type of sealed section:  Approx. 1 meter of bentonite pellets

Pump description:    1.0 hp mono-phase electric submersible

Depth to base of pump:   76 meters

Flow rate:    2,300  liters/hour

Water analysis results: Not yet tested

 